Please note that all connections to the NOTL Hydro grid must be parallel and the costs are:

 
Please note that FIT projects must pass an OPA screening prior to Niagara-on-the-Lake Hydro proceeding with a Connection Impact Assessment (CIA).  CIA fees are as follows:
     
Single Phase Bi-directional meter for 200A or less service : $600+HST

3 Phase Bi-directional meter: $1200 +HST

 
Projects <= 500kW       $4,250.00
Projects <= 1mW          $5,500.00
Projects > 1mW            $8,000.00
 
*Charges in Canadian dollars, subject to HST.
 
 
There is a monthly FIT/MicroFIT service charge of $5.25 (plus HST)
An APPLICATION TO CONNECT to Niagara-on-the-Lake Hydro"s Distribution System is required for all FIT/microFIT projects.  Please complete APPLICATION TO CONNECT and return it to Niagara-on-the-Lake Hydro via one of the following methods:
  
Drop-Off at NOTL Hydro Office       
NOTL Hydro                                          
8 Henegan Road
Virgil ON, L0S 1T0
   
 
Mail to NOTL Hydro Office
(address above, PO Box 460)
 
Fax application to:
NOTL Hydro at (905)468-3861                      
ATTN: Kevin Sidey
    
 
Email copy of application to:
Kevin Sidey - Senior Engineering Technologist